StopPATH WV
  • News
  • StopPATH WV Blog
  • FAQ
  • Events
  • Fundraisers
  • Make a Donation
  • Landowner Resources
  • About PATH
  • Get Involved
  • Commercials
  • Links
  • About Us
  • Contact

FirstEnergy and AEP Flame Out in Ohio; Seek to Strap Ratepayers in Other States

5/3/2016

2 Comments

 
Well, that was completely unsurprising.  FERC said the Power Purchase Agreements requiring captive Ohio distribution company customers to purchase generation from AEP and FE merchant generators don't pass the sniff test.

Even though the Public Utilities Commission of Ohio (PUCO) approved the deals, FERC rules about affiliate transactions cannot be bypassed (or politically influenced).

FERC rescinded previously granted waivers to allow AEP & FE to engage in affiliate transactions without review.  The waivers were granted when the companies spun off their regulated generators into merchant companies because the generation companies no longer had captive customers.  In that case, any deals between regulated distribution affiliates and unregulated generation affiliates would have been subject to market forces.  If the deals were too expensive, then customers could bypass the charges and switch to another, cheaper, generator.  But AEP & FE made the mistake of placing the cost burden of these PPAs on captive distribution customers, and not free choice generation customers.  Because then the customers would choose a cheaper generator.

Contrary to some of the articles I've read, the FERC decision does not reverse the PUCO's decision to allow the cost of the PPAs to become the responsibility of captive distribution customers.  It simply rescinds its prior waiver of review of the PPA itself.  The companies are now free to submit the PPAs to FERC for review.  If FERC approves them, then everything can proceed as planned.  However, it is unlikely that FERC will approve the PPAs because they allow AEP & FE to charge their captive customers to subsidize their shareholders profits.

So, what's a greedy and poorly managed utility to do?  FE initially wanted to pretend that its PPA will be found just and reasonable by FERC.  How much money and political influence would THAT require?  Remember, the cost of civic and political activities is the financial responsibility of shareholders, not ratepayers.  The cost of buying FERC is likely to obviate any temporary profits that may come from an 8-year PPA.  They're not a cheap date like state utility commissions.  However the company has apparently crunched the numbers and come to its senses.  FE is now attempting to bypass FERC review by doing away with the PPA, while still collecting the charge it would levy on Ohio consumers.  AEP is being a little more realistic, if not downright arrogant.  AEP's CEO soothed investor agitation by claiming it will make the Ohio legislature re-regulate generation so that it may collect the cost of service, plus a return, for its Ohio generators.  This would effectively end retail generation choice in Ohio.  Is legislation that will cost Ohio electric ratepayers more money really that easy for AEP that it simply needs to want it and wave its magic wand?  Time will tell.

Meanwhile, FirstEnergy wants to make its regulated Mon Power and Potomac Edison affiliates in West Virginia purchase another non-competitive generator from its competitive generation affiliate.  It's just like re-regulating generation in Ohio, but the legislative work is already done.  And FirstEnergy has already successfully pulled off a similar affiliate transaction a couple years ago when its competitive generation affiliate "sold" the Harrison Power Station to regulated Mon Power and Potomac Edison.  West Virginia electric consumers have already bailed out one of FirstEnergy's uncompetitive generators, what's one more?  This time, FE wants to "sell" its Pleasants Power Station to Mon Power and Potomac Edison.  But Mon Power already owned an 8% share of Pleasants, which it "sold" to FE Generation as part of the Harrison deal.  Now FE Generation wants to sell the same power station back to Mon Power.  Pleasants is like the FE hot potato, bought and sold among affiliates as necessary to generate cash.  The only fly in the ointment this time is that FE put a price on Pleasants when it "sold" it last time.  I'm sure the cost to Mon Power can't be more than what FE Generation paid them for the plant a couple years ago.  It's not like the price of antique coal generation stations has shot up in the past few years.  But, never fear, I'm sure FE can pay the right people to convince the WV PSC that the plant is as valuable as the amount of cash FE needs to raise from its sale.

And don't forget... all this stashing of competitive generators into regulated companies is only temporary.  If power prices recover and these generators once again become competitive, AEP & FE will find a way to "sell" these plants back to their competitive generation companies.  It's all about shareholder return and making as much money as possible.... and ratepayers are the source of investor owned utility profits.  The idea that regulation protects consumers in the absence of competition is nothing more than a fig leaf.  Utilities that operate in both a competitive and regulated environment will continue to shift assets around to generate the most profit for their shareholders.
2 Comments

How Much Do You Want to Pay Environmental PIGs to "Represent" You at FERC?

3/9/2016

4 Comments

 
Warning... this is going to be a long one.  Like a terrifying octopus, this issue has tentacles going in all directions.  Hopefully I can follow them all, so that you, little consumer, can follow along and perhaps act in your own interests down the road.

Let's start with the good news -- FERC has approved ratepayer funding for the Consumer Advocates of the PJM States (CAPS) to participate in PJM matters.  This is good news for consumers in the PJM region who don't have time or inclination to participate in PJM's countless stakeholder proceedings.  CAPS is made up of "state advocate offices designated by the laws of their respective jurisdictions to represent the interests of utility consumers within the service territory of PJM...".  These state consumer advocates are overworked and underfunded for all they do on behalf of residential electric customers. 

One caveat in the Order, however, says that CAPS funding may only be used for "staffing and travel costs for state consumer advocates to participate in in-person meetings and other proceedings at PJM as well as to pay professional staff and operation of the CAPS organization."  This also includes "participation in other Commission activities, such as responding to Notices of Proposed Rulemakings and participating in Technical Conferences."  CAPS funding may not be used for "(1) activities related to proceedings of state agencies;  (2) proceedings at federal agencies other than the  Commission; (3) litigation of matters at the Commission arising from the filing of Tariff or Operating Agreement changes by PJM including the filing of interventions or protests or participation in hearings or settlements; or (4) the hiring of counsel or expert witnesses to support the filings of other parties."

However, Commissioner Tony Clark dissented, stating:
This Commission has not before endorsed the policy that the activities of non-decisional
intervenor groups be funded through a dedicated utility tariff under the auspices of the FPA. Yet here we are doing exactly that. Today’s order is couched in the language of
good intentions, but I find it troubling  precedent as both a matter of policy and prudence.
Commissioner Clark said that this Order "cracks open Pandora's box," and before the ink was even dry on the Order and the Dissent, that's exactly what happened.  Clark wondered:
My public policy concern is that there is little that meaningfully differentiates these
organizations from a myriad of other state agencies and not-for-profit governmental
organizations or other interest groups that will now say, “what about my piece of the
pie?” CAPS entities argue they are uniquely situated. But aren’t state energy offices, in
their own way, also uniquely situated? What about state departments of environmental
quality? Do they, too, deserve a Regional Transmission Organization (RTO) funded
organization to finance their participation in stakeholder meetings? Furthermore, given
that CAPS includes at least one non-governmental non-profit, we now have cracked-open the lid of Pandora’s Box just a little wider yet. What is to stop any of the countless groups that intersect with the regulatory world from arguing that they are also uniquely situated to speak for any  number of communities of interest?
Which brings us to... Monday, when the very PIGs (Public Interest Groups) Commissioner Clark was concerned about filed a rulemaking petition looking for their own piece of the pie.

It's no secret that Public Citizen has been harping on FERC for years to set up the Office of Public Participation which was authorized by Congress back in 1978.  That's 38 years ago, folks.  And Public Citizen just now thought about filing a Petition for Rulemaking?  That's some stellar FERC work right there!  Thirty eight years ago, a leisure-suited Congress authorized such an office, along with a funding stream to compensate "persons under this subsection" through the year 1981.  What is new is that Public Citizen now wants its piece of the "person" pie!  And Public Citizen has brought along an entire herd of hungry PIGs to gobble up what it believes should now be a $6.5M yearly pie.  The petition was signed by 31 self-appointed PIG "advocates" for consumers and the environment, and not a state advocate office designated by the laws of their respective jurisdictions to represent the interests of utility consumers in the bunch.

The hungry PIGs are a hodge-podge of "consumer interest" groups you've never heard of, environmental organizations, "coalitions," "projects," "centers," "councils," "institutes," "partnerships," and an "investment corporation."  I've never seen many of these groups doing much of anything at FERC, and I haven't seen them litigating actual rate cases that save consumers real money.  The few I have seen poking their stick into the FERC lion cage are more interested in policy issues, such as championing environmental interests before the Commission.  These organizations are already very well funded through grants and gifts to advocate for the environment.  Do they deserve public money for carrying out their political goals?  These aren't public interest groups, they're specialty interest groups.

Let's look at just a couple on the list.  Public Citizen describes its climate and energy program as:  "Public Citizen's energy and climate program advocates for affordable, clean and sustainable energy. We safeguard families by promoting the strong regulation of energy markets, educate the public on the dangers of continued reliance on dirty energy sources, help solve climate change by promoting localized clean energy alternatives and hold large energy corporations accountable by exposing wrongdoing."  The group's Form 990s available here and here describe their Energy Program as:  "Provides information to the public on the threat of catastrophic climate change, the dangers of nuclear and fossil fuels, and the opportunities available to advance energy efficiency and develop renewable energy solutions."  And they show a whole lot of income from mysteriously unnamed donors, and grants to clean energy programs.  And they also show that Public Citizen has its fingers in a whole lot of political issue pies, not just energy.  Their "Accomplishments" page is devoid of any victories at FERC.  I'm not convinced that Public Citizen is substantially contributing to important issues at the Commission, or that any participation by Public Citizen presents a "financial hardship" for their "person."

At the other end of the PIG roll, A World Institute for a Sustainable Humanity describes itself as:  "A World Institute for a Sustainable Humanity (A W.I.S.H.) is an international nonprofit organization whose mission is to provide models and support for life sustaining activities that integrate solutions to poverty and the environment while fostering self-reliance. It was founded in March of 1995 and is registered as an NGO in fourteen countries and states."  A search of FERC's eLibrary for this organization brings up nada.  I'm not convinced they have ever done anything at FERC that contributed to any substantial issues.

This seems more like a "build the funding and they will come" pipe dream.
So, what does the 1978 law say, anyhow?
(a)
(1) There shall be an office in the Commission to be known as the Office of Public Participation (hereinafter in this section referred to as the “Office”).
(2)
(A) The Office shall be administered by a Director. The Director shall be appointed by the Chairman with the approval of the Commission. The Director may be removed during his term of office by the Chairman, with the approval of the Commission, only for inefficiency, neglect of duty, or malfeasance in office.
(B) The term of office of the Director shall be 4 years. The Director shall be responsible for the discharge of the functions and duties of the Office. He shall be appointed and compensated at a rate not in excess of the maximum rate prescribed for GS–18 of the General Schedule under section 5332 of title 5.
(3) The Director may appoint, and assign the duties of, employees of such Office, and with the concurrence of the Commission he may fix the compensation of such employees and procure temporary and intermittent services to the same extent as is authorized under section 3109 of title 5.
(b)
(1) The Director shall coordinate assistance to the public with respect to authorities exercised by the Commission. The Director shall also coordinate assistance available to persons intervening or participating or proposing to intervene or participate in proceedings before the Commission.
(2) The Commission may, under rules promulgated by it, provide compensation for reasonable attorney’s fees, expert witness fees, and other costs of intervening or participating in any proceeding before the Commission to any person whose intervention or participation substantially contributed to the approval, in whole or in part, of a position advocated by such person. Such compensation may be paid only if the Commission has determined that--
(A) the proceeding is significant, and
(B) such person’s intervention or participation in such proceeding without receipt of compensation constitutes a significant financial hardship to him.

(3) Nothing in this subsection affects or restricts any rights of any intervenor or participant under any other applicable law or rule of law.
(4) There are authorized to be appropriated to the Secretary of Energy to be used by the Office for purposes of compensation of persons under the provisions of this subsection not to exceed $500,000 for the fiscal year 1978, not to exceed $2,000,000 for the fiscal year 1979, not to exceed $2,200,000 for the fiscal year 1980, and not to exceed $2,400,000 for the fiscal year 1981.
So, any funding to "persons" is contingent upon the participation substantially contributing the approval of that person's position.  This is not an advance funding free-for-all for PIGs to suddenly access funds to create their own offices to participate in FERC ratemaking.  Funding only comes AFTER a "person" wins a case.  The proceeding also must be "significant," whatever FERC wants to presume that to be.  Such "person's" participation must also present a "financial hardship."  That's a conundrum.  If a person can only collect funding after their position is approved by the Commission, then said "person" would have already spent the money to participate, without knowing in advance if they will prevail, or whether the proceeding is "significant."  If the money has been spent without promise of funding, then how could the "person" then make a case of financial hardship?  If it's a true financial hardship, they'd never be able to participate in the first place.  For real people, every dollar they spend on lawyers and experts is one dollar less they can spend on hot dogs and tickets to the ball game.

Public Citizen then goes on to quote the Congressional Record from 1978, which makes clear that Congress intended this public participation to come from "electric consumers," or "individuals."  I don't see anything in there about PIGs.  After all, any "person" could declare that their efforts were "for consumers," and attempt to score some public funding for participating at the Commission, even utilities, or utility industry coalitions or associations, such as EEI.  Who knows what will pop out of Pandora's box?

Case in point... after blathering on about how the idea for the Office of Public Participation was based on public participation by electric ratepayers, in ratemaking, Public Citizen says this:
The Office of Public Participation is also needed to provide support to communities involved with FERC-jurisdictional hydro and natural gas infrastructure proposals.
Funny that.  The Delaware Riverkeeper Network also used FERC's failure to create the Office of Public Participation and fund intervenor costs as an example of FERC's "bias" in its recent lawsuit filed against the Commission in U.S. District Court.  While I have the utmost sympathy for individuals personally affected by fracking and pipelines, I have no respect for the environmental groups who use these folks as battering rams to accomplish their environmental goals.  That lawsuit was painful to read and I can't imagine a court wasting much time on it.  Just because funding for FERC's gas program comes from gas companies does not create bias.  The annual costs for the program are allocated to gas companies based on their usage.  The Commission would be funded whether or not they approved new pipeline applications, because gas will continue to flow.  Adding new pipelines to the stable simply spreads out the costs among a larger herd.  It does not increase FERC's "take," nor pay dividends to FERC employees to approve pipelines.  The continual attacks on FERC (both judicial and in person at the facility) aren't helping the cause.  About the only good argument in the whole lawsuit relates to requests for rehearing, and FERC has already handled that.  And that's oftentime the problem with environmental and other group participation that comes from "outside" FERC's little specialty practice arena.  It can be clueless about process, laws, and even FERC's jurisdiction to act in the first place.  I'm not sure adding more misinformed voices to the shuffle is prudent or helpful.  If you want to participate at FERC, make it meaningful.  Don't just carry on at monthly meetings, interrupting every other hearing underway in the building, because you're angry and unsatisfied with your own ignorance of the process.  Educate yourself!

And be careful what you wish for.  In discussions with grassroots groups in states with a mechanism for intervenor funding for participation in public utility cases, the same complaint comes up over and over.  They allege that well-heeled and well-connected PIGs are always first in line at the funding trough, and there is precious little left over for the folks who are actually on the front lines of energy projects and rate increases.  Oftentimes the PIGs use their funding to weigh in on the side of the utilities, especially to enable construction of renewable energy infrastructure.  PIGs don't care about you, little ratepayer or landowner.  They really don't.

Funding PIGs to carry on in a nonsensical manner at FERC is a bad idea.  Let's see if FERC actually notices a proposed rulemaking on this issue, or simply bats it aside as more PIG mischief.
4 Comments

FERC Takes On ISO-NE Formula Rates

1/14/2016

0 Comments

 
FERC continues its focus on transmission formula rates, recently opening an investigation into ISO-NE's processes.  This follows FERC's investigation into MISO formula rates several years ago.

In its December 28 Order, FERC set the justness and reasonableness of ISO-NE's RNS and LNS formula rates and the development of protocols for hearing.  FERC said the current formula rates lack transparency and sufficient detail to determine how certain costs are derived and recovered.  The rates also lack sufficient protocols to ensure the data is correct, calculations are performed correctly and that the charges are reasonable and prudent.  The protocols also lack sufficient notice, review, and challenge procedures for interested parties.

There seems to be some concern over the timing and synchronization between RNS (regional) and LNS (local) rates.  Currently, transmission owners submit their own revenue requirements for a combined RNS formula rate, in addition to individual LNS rate filings.

This article in the NH Union Leader presents a handy-dandy graph of transmission costs in different regions.  ISO-NE's transmission charges are nearly double those of second place transmission rate champion, PJM.  Does ISO-NE really have that much more transmission, or are things simply out of control on the formula rate front that allows "errors" to boost annual revenue requirements with bogus charges?

Who's currently monitoring whether transmission owners are doubling their return by including the same costs in both RNS and LNS formula rates?  FERC's Order says its impossible to determine right now.

And what if companies like Eversource are accidentally including costs for things, like advertising for their Northern Pass project, in RNS/LNS rates collected from ratepayers, instead of including them in the transmission service agreement costs formula rate to be paid by HQ Hydro?  All sorts of "mistakes" could happen in the current rate scheme.

Who's minding the store up there?  FERC says ISO-NE currently has an option to audit the RNS/LNS rates, but I wonder how much real auditing actually happens?

Good thing that FERC is taking on the challenge of shedding a little light into ISO-NE formula rates.  But the work doesn't stop there... even the best formula rates and protocols are useless unless someone takes advantage them to actually take a look at the rates on a yearly basis, long after FERC's work here is done.

Good luck on getting a handle on your transmission costs problem, New England!
0 Comments

Clean Lies About Iowa Ratepayer Benefits

1/13/2016

0 Comments

 
Do you often make a typo that turns "Clean Line" into "Clean Lie?"  Me, too.

Clean Line has a new shtick that claims Iowa ratepayers will benefit if the IUB allows it to change the process to make it less costly for its investors.  Clean Line's claim can be paraphrased like this:

If you don't make it easy for us to build the Rock Island Clean Line (RICL) using the merchant model that charges customers in other regions for the cost of the project, then the Midcontinent Independent Systems Operator (MISO) will order new transmission just like RICL and make Iowa ratepayers pay for it.

Clean Line must really think Iowans and their Utility Board are a bunch of rubes.  This argument fails on so many levels, and the reality is that building RICL could actually increase electricity costs for Iowans.

First of all, this is an apples to oranges comparison.  RICL is not at all like the transmission projects MISO may order to be built.  RICL's stated purpose is to export electricity from the MISO region to the PJM Interconnection region.  MISO generally serves midwestern states, while PJM generally serves eastern states.  RICL proposes to move large quantities of electricity generated in MISO into PJM, where it may be used by "states farther east."  RICL is not proposing to serve any customers in MISO, particularly in Iowa.  Contrast that to the transmission projects MISO orders.  MISO is concerned only with serving customers within its own region.  Therefore, any transmission projects MISO orders will be for the purpose of moving electricity around the MISO region for use by MISO consumers.  MISO would never propose a transmission project for the express purpose of exporting electricity to another region, and then turn around and expect MISO consumers to pay for it.

Independent System Operators and Regional Transmission Organizations (which are generally identical constructs) are quite parochial.  They are utility member organizations that exist to serve their own regional interests.  Interregional planning is extremely fragile, to the point of being non-existent.  This is because an ISO/RTO will generally utilize its own resources first, from a cost and reliability standpoint, before importing resources from another region.  RTO/ISO members would never agree to pay the cost of export to another region, and moreover, this rubs against the Federal Energy Regulatory Commission's Order No. 1000, that ensures that only beneficiaries pay the cost of transmission built to serve them.

Therefore, the building of RICL would have NO EFFECT on the transmission projects MISO orders to serve its consumers.  MISO will still order the transmission it needs to serve consumers in its region, including Iowa.  RICL is no substitute for MISO-ordered transmission because it would not serve any consumers in Iowa, or anywhere in the MISO region.  At best, RICL is agnostic about costs to Iowa ratepayers.  It certainly won't save them any money.

RICL may actually cost Iowans higher electricity prices.  Think of electricity produced in Iowa as a reservoir.  As long as supply is plentiful, prices remain cheap, and cheap energy is dispatched first to Iowans.  However, RICL would turn on a gigantic tap that drains that reservoir and sends the water (or electricity) to other regions with higher prices.  This creates an imbalance between supply and demand, where Iowa electricity buyers must now compete with other regions to buy the cheapest Iowa-produced electricity remaining in the reservoir.  Transmission lines levelize prices between electricity's source and sink (consumers), lowering prices in other areas by making cheaper energy available to new users, while raising prices at its source by increasing competition for the newly-limited supply.  Exporting a plentiful supply of anything raises local prices by lowering supply.  It's the simple principle of supply and demand.

Clean Line has come dangerously close to violating its negotiated rate authority granted by the Federal Energy Regulatory Commission.  FERC based its grant of authority, in part, on the following:

To approve negotiated rates for a transmission project, the Commission must find that the rates are just and reasonable. To do so, the Commission must determine that the merchant transmission owner has assumed the full market risk for the cost of constructing its proposed transmission project.

Rock Island meets the definition of a merchant transmission owner because it assumes all market risk associated with the Project and has no captive customers. Rock Island has agreed to bear all the risk that the Project will succeed or fail based on whether a market exists for its services.
What RICL proposed in Iowa is a shifting of risk to Iowans.  RICL believes it should not be subject to the financial risk presented by Iowa's long-standing permitting process that requires it to negotiate voluntary easements or prepare time-consuming Exhibit E material before being granted a permit.  Instead, RICL believes Iowans should be subject to a confusing, inconvenient, and more costly bifurcated permitting process in order to absolve RICL of any financial risk during the permitting process.  This is a shifting of financial risk to Iowans.

In its application to FERC, RICL talked big about sharing the risk with its customers, the load-serving entities (LSEs) that would buy its capacity.
Rock Island also argues that wind generators, whose energy the Project will likely transmit, present numerous risks that transmission project developers and investors must overcome. For example, Rock Island states that wind energy projects are typically constructed with shorter lead times than other generators and are less willing to commit to large transmission projects well in advance of generator construction. Rock Island argues that pre-subscription of capacity with creditworthy anchor customers can reduce financing obstacles because lenders demand to see a secure source of revenue as a predicate to project financing.
Here, it appears that RICL is suggesting that it can sell its capacity to LSEs before the project is built.  These entities with a guaranteed spot on RICL's wind highway would later buy electricity from wind farms connected to RICL.  Not only would it lower RICL's financial risk by providing the company with capital before its project is online, it would also provide a future revenue stream that wind farms could use to secure their own financing.  Perhaps RICL should be looking to share its financial risk in Iowa with its potential customers by pre-subscribing its capacity to LSE customers at this time?  Let the LSEs pony up the funds necessary to negotiate voluntary easements or create Exhibit E materials.  That would shift the financial risk from RICL to its customers, where it belongs, instead of to Iowans.

Except RICL doesn't have any customers.  Potential customers have been unwilling to shoulder any of RICL's financial risk during the permitting process.  Chicken/egg.  This demonstrates why Clean Line's business model will never work unless states agree to shift Clean Line's risk onto their own citizens by permitting a project that has no customers.  Iowa said no on Monday.  Arkansas said no in 2011.  Missouri said no last summer.

In order to hide its failure to share risk with its own customers, RICL whined that the Iowa process is flawed and must be changed to shift risk from RICL to Iowans.

I'm not buying it.  How about you?
0 Comments

No RTO Membership Incentive for You, PATH

12/18/2015

1 Comment

 
Yesterday, FERC issued an Order Denying Rehearing of its earlier decision to deny PATH an additional half a percent of return on equity for its membership in PJM.

The Commission explained again that because PATH never (and will never) turn any transmission lines over to PJM for operation that it is no longer eligible for the incentive bonus point adder.

End of that chapter.  More PATH saga to come....  stay tuned.
1 Comment

FERC to "Further Consider" PATH's ROE Rehearing Request

12/15/2015

1 Comment

 
The Federal Energy Regulatory Commission has added reconsideration of PATH's request for rehearing of the Commission's denial of its RTO membership incentive adder to the agenda of its monthly meeting scheduled for Thursday.

It's been so long since the Commission granted rehearing on this limited matter, it's been nearly forgotten in the ensuing shuffle.

At issue is PATH's request to continue to collect a half a percent of extra incentive return on equity for its membership in PJM Interconnection.  When the Commission granted PATH a whole bunch of incentives back in 2008, it also granted it an additional 50 basis points for joining PJM.  PATH proposed that it be allowed to continue to collect this incentive after it abandoned the PATH project, by continuing its membership in PJM until it had finished collecting its abandoned plant.

The Joint Consumer Advocates answered PATH's request for rehearing, and pointed out that the stated purpose of section 219 is to provide incentive-based rate treatments that benefit consumers by ensuring reliability and reducing the cost of delivered power.
  The PATH project has not benefited consumers by ensuring reliability because it was never built.  And it certainly never reduced the cost of delivered power.  Quite to the contrary, PATH increased the cost of delivered power by leaving ratepayers on the hook for its $121M of development costs even though it never even put a shovel in the ground.

In other words, even though PATH will never be built, and the PATH companies will cease to exist as soon as their abandoned plant is collected from ratepayers, PATH wants to be financially rewarded for continuing its pointless membership in PJM.  A membership in PJM allows the member to participate in the PJM transmission planning process.  Since PATH won't be built, and since the PATH companies were single purpose entities that will never plan or build another transmission project, what's the point of their continued membership in PJM?

I think the point is to continue to collect an additional half a percentage point of return (or interest) on the slowly dwindling $121M abandoned plant balance that PJM ratepayers must pay for.

It will be interesting to see what the Commission does to dispose of this matter.
1 Comment

FERC Upholds Consumer Standing to File Rate Complaints

11/13/2015

5 Comments

 
Once again, the Commission has reaffirmed that electric consumers have the right to challenge wholesale electric rates that flow through to their local electric bills.
...the Commission concludes that, as courts have recognized, retail customers may file complaints and protest transmission rates and wholesale sales rates before the Commission.  Moreover, allowing retail customers to challenge such rates does not violate principles of federalism or interfere with states’ rights.
The settlement judge in a formal challenge proceeding involving a subsidiary of investor owned utility AEP had submitted what are known as "Certified Questions" to the Commission on Oct. 13.  A certified question is intended to seek the Commission's consideration and disposition of "any question arising in the proceeding, including any question of law, policy, or procedure."  The Commission had 30 days to answer the questions posed, otherwise they would revert to the judge who posed them for decision.  The questions posed were:
(1)  Shouldn’t section 306 of the Federal Power Act (FPA) be interpreted
in pari materia with section 201 of the FPA?  FPA section 201 gives the Commission jurisdiction over wholesale interstate rates and interstate transmission; therefore, retail ratepayers would not have the right to file complaints against wholesale rates.

(2) Wouldn’t an expansive interpretation of section 306 of the FPA (allowing retail ratepayers or end users to file complaints against interstate wholesale rates) violate the delicate balance of federalism; in other words, by giving complaint authority to retail rate customers, is the Commission interfering with states’ rights by asserting jurisdiction over retail rates?
The judge had recommended that the Commission:
answer the questions as follows: 
(1) “retail ratepayers are not permitted to bring an FPA section 205 complaint against wholesale sellers of electricity[;]” and (2) a different interpretation (i.e., allowing such retail ratepayer complaints) “would interfere with state jurisdiction over retail rates.”
The Commission didn't see it that way, and yesterday they issued an Order that explained to the judge:
Complaints may be filed under sections 206 and/or 306 of the FPA, 16 U.S.C. §§ 824e, 825e (2012).  While section 205(e) of the FPA refers to “complaints,” 16 U.S.C. § 824d(e) (2012), the Commission commonly refers to these filings as protests.  See 18 C.F.R. § 385.211 (2015).   

The plain language of the FPA and the Commission’s implementing regulations allow broad participation in proceedings before the Commission.  Specifically,
section 306 of the FPA explicitly authorizes “[a]ny person” to file a complaint with
the Commission. The Commission’s regulations are to a similar effect.  For example, Rule 206(a) of the Commission’s Rules of Practice and Procedures provides that “[a]ny person may file a complaint seeking Commission action against any other person alleged to be in contravention or violation of any statute, rule, order, or other law administered by the Commission or for any other alleged wrong over which the Commission may have jurisdiction.

Ms. Peine, an intervenor in this proceeding, is contesting the SWEPCO/AEP transmission formula rate inputs, and thus rates for transmission of electric energy in interstate commerce, which is within the Commission’s exclusive jurisdiction under Part II of the FPA.  These transmission inputs, i.e., costs, flow through to Ms. Peine’s retail electric bill.  Stated another way, Ms. Peine is an “end-use customer that will pay  . . . some portion of that [transmission] rate when flowed through [her] retail bill.” Thus, by challenging the transmission formula rate inputs, Ms. Peine has alleged injury in fact that can only be addressed by the Commission.  Under these facts, Ms. Peine is permitted to file a protest or a complaint and to participate in this proceeding by intervening.

This outcome is consistent with federalism.  Section 201 of the FPA recognizes the authority of the states over retail sales and facilities used in “local distribution.”  Ms. Peine’s formal challenges, however, go to the transmission formula rate inputs identified in the SWEPCO/AEP 2013 and 2014 Annual Updates.  Ms. Peine’s claims, therefore, go to the transmission of electric energy in interstate commerce and not to local distribution

Moreover, this issue is not a matter of first impression, as both the courts and the Commission have concluded previously that protecting consumers is one of the Commission’s primary responsibilities.

...the relevant definition of “interested parties” under the SWEPCO/AEP Protocols is not the version that was filed in 2007, but rather the version that was in effect when Ms. Peine filed her formal challenges under the Protocols, and that version did not include the examples that the Settlement Judge construed as limiting the definition of interested parties to exclude Ms. Peine.  Moreover, we disagree with the Settlement Judge’s interpretation of the parenthetical phrase in the earlier version of the SWEPCO/AEP Protocols.  The parenthetical phrase “(e.g., Transmission customers and affected state and federal regulatory authorities)” provided examples of categories of interested parties, and should not be read as exhaustive.  This parenthetical language would not preclude an end-use customer, like Ms. Peine, who will pay a portion of the transmission rate in her retail bill, from challenging the inputs to the SWEPCO/AEP transmission formula rate.

Lastly, as to the administrative efficiency concerns raised by the Settlement Judge and AEP, we note that the Commission’s Rules of Practice and Procedure provide appropriate measures to streamline Commission proceedings.
So, the judge made a complete mess of a whole bunch of law in her rush to deny standing to a ratepayer.  She also doesn't know the difference between "e.g." and "i.e."  And AEP and the Judge need to kwitcherbitchin about how terribly hard and unfair it is to utilities to have their rates examined by those who pay them.  Did they expect that the Commission was going to do away with annual reviews of formula rate inputs altogether?  There's no way to limit participation.  It's all in or nothing.  And the Commission just can't legally go with shutting down rate transparency.
Perhaps there's also a lesson here for AEP, who did a whole bunch of whining about how burdensome and costly customer reviews of wholesale transmission could be as an excuse to escape rate review altogether.  AEP has been down this road before as one of the parent companies involved in the PATH decision the Commission cited over and over in yesterday's Order.  Shame on you, AEP!  If someone suggested that you could steal from your grandmother and get away with it, would you do it?  Even though you know full well stealing from Granny is wrong?  I thought AEP was supposed to "do the right thing?"  Here's a little advice from your own CEO to apply the next time you see an opportunity to do something that you know is wrong in order to take unfair advantage over someone who appears to be weaker than you:
I urge you to make the concepts described in this book a regular point of reference for the manner in which you carry out your work and the treatment of others.
Karma.
5 Comments

Powhatan v. FERC:  Showdown at the U.S. District Court Corral

11/10/2015

2 Comments

 
The U.S. District Court for the Eastern District of Virginia looks like the O.K. Corral in the aftermath of the recent paper showdown requesting dismissal of FERC's petition to request an Order Affirming the Commission's Order Assessing Civil Penalties of $34.5M against defendants Powhatan Energy Fund and Alan Chen.

On October 19, Powhatan and Heep Fund, et. al. (Chen defendents) filed Motions to Dismiss FERC's request prior to trial.

The Powhatan Motion to Dismiss relies on FERC's failure to provide fair notice that the trades at issue were illegal at the time they took place.  Powhatan says this raises serious due process issues.

The Heep Fund Motion to Dismiss relies on a contention that the statute of limitations had expired before FERC's filing in U.S. District Court for all but 4 days of the subject trading.  Heep Fund also says that the complaint does not state a claim for market manipulation.  They also claim the same due process issues raised in Powhatan's Motion.  And, finally, Heep contends that the FPA does not authorize manipulation claims against individuals like Dr. Chen.

FERC responded on October 30, claiming Fair Notice precedent supports their claim and that Powhatan mischaracterizes the Commission's actions and precedent, and that none of their claims have merit.  FERC's response to Heep Fund made similar claims that their Motion to Dismiss was all wet.

What I found interesting here was FERC's reading of its Black Oak precedent as recognizing that traders may make trades solely to capture MLSA payments, however FERC "fixed" that problem by requiring traders to also purchase transmission.


In March 2009, PJM followed the narrower approach, proposing to pay MLSA to all trades with paid transmission (physical or virtual). In response to that filing, no party suggested that UTC trading would be susceptible to the kind of perverse incentives that the Commission understood could apply to most virtual trades.

No party filed any comments rebutting this contention as to the narrow distribution method, and the Commission accepted it in September 2009. Black Oak Energy, LLC, et al. v. PJM Interconnection, L.L.C., 128 FERC ¶ 61,262 (2009).
So, the Commission believed it had closed any loophole that created an incentive to place trades with the intention of collecting MLSA payments by requiring traders to purchase transmission.  But it didn't.  And the trading happened.

FERC contends, nevertheless, that the trading was an illegal type of trading, and in an effort to build a villain it uses the word "Enron" 19 times.  Everybody knows that Enron was bad, right?  And because this whole issue is so technical and hard to think about, maybe people will just go with the bad aura created by glittering generalities?  Here's another:  FERC used the words "Death Star" 17 times.  No average Joe knows what "Death Star" trading is, but it conjures up images of our Star Wars heroes being in jeopardy.  And it sounds really, really bad!!

FERC also prattles on about the Powhatan & Chen defendant's trading depriving other market participants of MLSA payments they would have scored if the defendants didn't trade.  But in this alternate universe where the defendants didn't trade, might others have traded instead, which would throw off any entitlement to MLSA payments by the other market participants?  And FERC has still failed to convince me that the MLSA payments would have flowed through to the electric rates paid by customers of the other market participants, instead of into the corporate coffers that pay share dividends.  Since FERC can't explain this properly, it must not be true that the other participants failure to receive MLSA payments caused higher rates for electric consumers.  I'm still waiting here...

Yesterday, Powhatan and Heep filed Rebuttals to FERC's responses.

Powhatan pointed out that FERC has changed its position on what the Black Oak orders meant, and "misses the forest for the trees."  Powhatan also points out a gap in FERC's logic:  If the Black Oak orders prohibited the trading at issue, why did FERC find it necessary to change the tariff to prevent this kind of trading AFTER it discovered what the defendants had done.  By closing the barn door after the horse got out, the Commission can now only retroactively fine Powhatan for trading that wasn't illegal when it happened.  And, of course, that idea is preposterous.

The Heep Rebuttal also refuted FERC's contentions in its Response.

So, now we'll see if the rocket docket
blasts off towards the Death Star, or dismisses this case, once the smoke clears in the corral.
2 Comments

FERC Flipping the FPA on its Head?

11/6/2015

0 Comments

 
Well, here's another article about FERC's recent confusion over consumer standing to file complaints at the agency.
In addition to airing her jurisdictional and standing concerns, the judge said permitting retail ratepayers to file such complaints "is at odds with promoting efficiency" because FERC could be faced with handling "potentially millions of individual complainants."

The groups, however, insisted that Cintron's position is "contrary to the plain language of the FPA," which states that "any person" has standing to file a complaint with FERC, as well as long-standing commission precedent holding that retail ratepayers have standing to challenge wholesale rates.

Citing a proceeding involving the abandoned Potomac Appalachian Transmission Highline project in which FERC found that "[a] complaint regarding a transmission rate can … be filed by any person, including an end-use customer that will pay some portion of that rate when flowed through its retail bill," the groups called Cintron's attempts to distinguish that situation from AEP's "unavailing." The judge relied on differences in the two companies' formula rate protocols to make her case, but the groups argued that "standing is a statutory right under the FPA, and whatever is said in the AEP protocol cannot overturn the statute."

As for Cintron's concerns about the regulatory burden that would be placed on FERC if retail ratepayers are allowed to challenge wholesale rates, the groups insisted that "administrative convenience is not a basis to eviscerate a statutory right." They said that "[i]n any event, this is a chimera — in the nearly 20 years since the commission issued Order 888, there has been a stream but not a deluge of … rate challenges."

Finally, among other things, the groups said the "novel viewpoint" expressed by Cintron "would reopen the … regulatory gap between federal and state jurisdiction that the FPA was designed to close."

"For consumers impacted by commission-jurisdictional transmission rates, there is no other effective remedy," the groups said.
And there's more new filings on the Docket.  (ER07-1069-006).
0 Comments

Can States Regulate Interstate Electricity Markets?

11/5/2015

2 Comments

 
It is long settled law that FERC has jurisdiction over interstate transmission rates.  State Commissions are required to respect that jurisdiction and cannot change transmission rates that flow through to the retail electric customers over which the states have jurisdiction.  A state must pass interstate transmission rates through unscathed.  A rate can only be changed in the jurisdiction in which it is set.  Therefore, any retail customer who pays an interstate transmission rate can only address it at FERC, where the rate was set.

Power Magazine published an interesting piece yesterday headlined, "Will FERC Bar Retail Customers From Electricity Cases?"
Should retail electricity customers be barred from bringing cases before the Federal Energy Regulatory Commission, a decades-long practice? A FERC administrative law judge, Carmen Citron, last month recommended to the commission that it abandon its long-standing practice and deny retail customers standing before the agency.

Cintron’s mid-October recommendation came in a case involving an Arkansas lawyer, school teacher and activist (ER07-1069-006), Martha Peine of Eureka Springs, Ark. She challenged expenses AEP subsidiary Southwestern Electric Power Co. charged to consumers in lobbying for a new interstate power line. She argued at FERC that SWEPCO had stuck customers with some $92,000 in expenses that were improper. Her filing was under Section 205 of the Federal Power Act (FPA).
The op-ed took a look at both Judge Cintron's "Certified Question" to the Commission, and the "swift and pointed response" to the question by numerous trade orgs. representing large industrial and commercial electricity users.  Power says the trade filing from ELCON
challenged Cintron’s reasoning as flipping “the fundamental purpose of the FPA on its head.”

Elcon asserted, “The purpose of the FPA is not to protect utilities from the burden of responding to consumers; rather, as the Supreme Court and other courts have recognized, it is ‘to protect power consumers against excessive prices.’”
ELCON's filing is powerful -- must read!

Power opined:
Whether retail customers can continue their historic right to access to FERC also has political implications for the commission. In recent months, anti-natural gas activists have staged demonstrations at commission meetings, including interrupting proceedings (resulting in guard-escorted exits from FERC’s D.C. headquarters). The protesters have argued, often at high volume, that FERC cares only for the interests of big energy companies, and not those of people affected by the agency’s actions.

The commission has repeatedly said, as it opens its monthly public meetings, that it will consider arguments and protests to its activities from anybody, through normal FERC proceedings, including filings. Should the commission adopt Cintron’s recommendations, those statements will ring administratively and politically hollow.
This sort of begs a question about who FERC serves, doesn't it?

The whole history of this legal quagmire can be found on FERC Docket No. ER07-1069, sub docket 006 (although FERC misdocketed one of the supporting memorandums on the main docket, instead of the sub.)  Interesting reading!


At any rate, the Commission has until Nov. 12 to decide the Certified Question, or else it will revert back to the judge for decision.

What do you think the Commission should do?

A couple of new parties have spoken this morning.  The  National Association of State Utility Consumer Advocates and the City of Coffeyville, Kansas, have filed support of ELCON's position and are asking the Commission to publicly notice this issue and accept public comment before making a decision.
2 Comments
<<Previous
Forward>>

    About the Author

    Keryn Newman blogs here at StopPATH WV about energy issues, transmission policy, misguided regulation, our greedy energy companies and their corporate spin.
    In 2008, AEP & Allegheny Energy's PATH joint venture used their transmission line routing etch-a-sketch to draw a 765kV line across the street from her house. Oooops! And the rest is history.

    About
    StopPATH Blog

    StopPATH Blog began as a forum for information and opinion about the PATH transmission project.  The PATH project was abandoned in 2012, however, this blog was not.

    StopPATH Blog continues to bring you energy policy news and opinion from a consumer's point of view.  If it's sometimes snarky and oftentimes irreverent, just remember that the truth isn't pretty.  People come here because they want the truth, instead of the usual dreadful lies this industry continues to tell itself.  If you keep reading, I'll keep writing.


    Need help opposing unneeded transmission?
    Email me


    Search This Site

    Got something to say?  Submit your own opinion for publication.

    RSS Feed

    Archives

    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012
    September 2012
    August 2012
    July 2012
    June 2012
    May 2012
    April 2012
    March 2012
    February 2012
    January 2012
    December 2011
    November 2011
    October 2011
    September 2011
    August 2011
    July 2011
    June 2011
    May 2011
    April 2011
    March 2011
    February 2011
    January 2011
    December 2010
    November 2010
    October 2010
    September 2010
    August 2010
    July 2010
    June 2010
    May 2010
    April 2010
    March 2010
    February 2010
    January 2010

    Categories

    All
    $$$$$$
    2023 PJM Transmission
    Aep Vs Firstenergy
    Arkansas
    Best Practices
    Best Practices
    Big Winds Big Lie
    Can Of Worms
    Carolinas
    Citizen Action
    Colorado
    Corporate Propaganda
    Data Centers
    Democracy Failures
    DOE Failure
    Emf
    Eminent Domain
    Events
    Ferc Action
    FERC Incentives Part Deux
    Ferc Transmission Noi
    Firstenergy Failure
    Good Ideas
    Illinois
    Iowa
    Kansas
    Land Agents
    Legislative Action
    Marketing To Mayberry
    MARL
    Missouri
    Mtstorm Doubs Rebuild
    Mtstormdoubs Rebuild
    New Jersey
    New Mexico
    Newslinks
    NIETC
    Opinion
    Path Alternatives
    Path Failures
    Path Intimidation Attempts
    Pay To Play
    Potomac Edison Investigation
    Power Company Propaganda
    Psc Failure
    Rates
    Regulatory Capture
    Skelly Fail
    The Pjm Cartel
    Top Ten Clean Line Mistakes
    Transource
    Valley Link Transmission
    Washington
    West Virginia
    Wind Catcher
    Wisconsin

Copyright 2010 StopPATH WV, Inc.